News: Compensation delay affects sh94b Luwero

F
Frederick Kiwanuka
News: Compensation delay affects sh94b Luwero
✦AI Summary

The construction of the Luwero-Butalangu road in Uganda has been significantly delayed due to pending compensation payments for affected residents. Government officials are working to clear these payments to allow the project to resume.

Why it matters

Infrastructure development is critical for regional economic growth, and delays highlight the complexities of land acquisition and public funding.

✦Dive DeeperCreate a free account to unlock

News: Compensation delay affects sh94b Luwero-Butalangu road

News Politics Education Health World Sports Business Tourism Blogs

Compensation delay affects sh94b Luwero-Butalangu road

The project was scheduled to be completed within a period of two years, which ended in June 2025.

The sh94b road, which had been scheduled to be completed by June last year, has dragged on up to today. (Photo by Frederick Kiwanuka)

Residents of Luwero and Nakaseke districts have run out of patience over the prolonged delay of

the 29km Luwero-Butalangu road that links the two districts.

scheduled to be completed by June last year,

commissioned by Prime Minister Robinah Nabbanja in June 2023, was being

However, nearly three years later, the contractor says they have

leaders and residents in the two districts, who say they are being inconvenienced by the heaps of murram, ditches and diversions

Continue reading on Headlinne

Create a free account to read the full article.

Read full article →
businessworldeconomy
✦

Get smarter about the news

Sign up free for a feed built around what you actually care about, Dive Deeper research on any story, and the full text of every article.

Create free account

Already have an account? Sign in